Georgia Pacific Wood Products - Corrigan, Texas
Challenge:
Design and install SEI's S3 Synergy technology into an existing ESP casing. Existing ESP is old with outdated technology.
Southern Environmental's Solution:
SEI performed physical model testing along with Computational Fluid Dynamics (CFD) to balance the air flow throughout the ESP system to maximize performance. SEI provided PowerPlus high frequency technology and SEI-ELEX electrodes while maintaining the current footprint.
Project Duration:
Purchase Order Received: December 19, 2012
Material delivered: May 1, 2013
Commissioning: July 20, 2013
Detailed Engineering in the following disciplines:
Civil
Structural
Mechanical
Electrical
1/8 Physical Model Study Completed with CFD
Fabrication and Construction Services:
ESP and Stack Access Fabrication
ESP and Stack Access Mechanical Installation
Electrical Installation
Civil Modifications
Field Technical Support and Commissioning
Scope of Work:
SEI provided detail engineering, material supply, fabrication, technical support, construction, physical flow model study, ash conveying system and roof system for a one chamber, two mechanical field electrostatic precipitator.
SEI designed and provided the rapper controller, PLC and PCAMS communication controls.
Guaranteed Outlet PM Emissions:
0.022lb/MMBtu with all fields in service.