Tampa Electric Company - Tampa, FL

Challenge: 

Unit 4 at TECO’s Big Bend Station due to its age was in need of a partial rebuild to meet its emission compliance requirements.  The two precipitators in a vertical arrangement made for a challenging demolition and installation effort during the constraints of a limited outage. 

teco roof.jpg

Southern Environmental’s Solution:

SEI provided a design, supply and install solution to upgrade the first two of a five fields in a dual chamber system.  The upgraded fields included SEI’s S3 – Synergy Design plus new electromagnetic rappers, access doors and key interlock system.  Maintenance services were applied to fields three, four and five which included a major overhaul of the tumbling hammer system.

Project Duration:

  • PO Received: July 5, 2013

  • Materials delivered: February 28 2014

  • Start-up: May 15, 2014

 

Detailed Engineering in the following disciplines:

teco.jpg
  • Structural

  • Mechanical

  • Electrical

 

Fabrication and Erection Services:

  • ESP Fabrication and Installation

  • Access Fabrication and Installation

  • Field Technical Support and Start Up

 

Guaranteed Outlet PM Emissions:

When tested after project completion the two field upgrade with SEI’s S3 Synergy design improved the ESP’s performance 64% to achieve a tested level of .008 lb/mmBtu.